8 December 2023
SNSA by decision confirmed the 3rd periodic safety review
More
18 November 2023
NEK Provides Electrical Energy Again
More
14 November 2023
Krško NPP is Expected to Produce Electrical Energy Again at the End of the Week
More
7 November 2023
The pipelines have been replaced; preparations are ongoing to restart the power plant
More
3 November 2023
The holiday week was a busy one at the Krško Nuclear Power Plant
More
26 October 2023
Determined Course and Scope of Remediation
More
24 October 2023
Commencement of Corrective Works to Eliminate the Deviation
More
18 October 2023
The Transfer of Fuel Elements from the Reactor Vessel Begins; the Elimination of the Deviation will Follow
More
11 October 2023
Measures following the Shutdown of the Krško Nuclear Power Plant
More
9 October 2023
The micro-location of the leak is determined, followed by analysis and the preparation of an action plan to eliminate the deviation
More
6 October 2023
Cold shutdown of Krško Nuclear Power Plant required to locate leakage
More
6 October 2023
Nuclear power plant shutdown to identify leakage location
More
6 October 2023
Preventive shutdown of Krško Nuclear Power Plant
More
21 June 2023
Annual Report: Even in conditions of great uncertainty in the supply of energy products and electrical energy, NPP retained high operating stability and effectiveness.
More
17 January 2023
Krško Nuclear Power Plant Gets Environmental Approval to Extend Its Lifetime from 40 to 60 Years
More