The pipelines have been replaced; preparations are ongoing to restart the power plant

On Saturday, the welding of the second new segment of the pipeline in the so-called valve room in the containment was completed. The quality of the welds was confirmed by non-destructive methods. With this, the replacement of pipelines was completed and preparations for restarting the power plant began.

According to the outage plan, 121 fuel elements are being transferred from the Spent Fuel Pool back into the reactor vessel. Once this transfer is complete, the heating of the systems will follow; their operation will be verified with an extensive surveillance testing program. We plan to synchronize the generator with the power grid in mid-November.

News

NEK Completes an Exceptional Operating Cycle and Enters the 2025 Planned Outage Nuclear Energy as the Foundation of a Stable Future

More
News

Successfully Completed Benchmark Visit for Cable Ageing Monitoring Programs

More
News

Annual Report: The first year in the plant’s extended operating life was extremely successful

More